How To Install AnglerFish Foot-steering Rudder
In this video, we show you how to install the rudder kit. For a downloadable PDF, see below.
Contents:
- Rudder
- Gudgeon
- 2 cable ties
- 2 cable tubes
- Lift line
- Bungee cord
- 2 steering lines
- 4 double line guides
- R pin
- 4 hooks
- 4 10-32 x 1” flat head screws
- 4 8-32 x 1 1/4” screws
- 4 #8-32 lock nuts
- D biner
- 2 s-biners
- Pad eye hook
- 6 cable clamps
- 6 8 x 1/2” flat head screws
- 4 10-32 x 5/8” oval head screws
- 8 #10-32 lock nuts
Tools needed:
- Drill
- 3/16 inch drill bit
- 1/8 inch drill bit
- 3/8 inch wrench
- #2 Phillips screwdriver
- Pliers
- Awl
Tools needed:
- Drill
- 3/16 inch drill bit
- 1/8 inch drill bit
- 3/8 inch wrench
- #2 Phillips screwdriver
- Pliers
- Awl
To start the rudder installation, partially assemble the AnglerFish by clamping the hull sections together and laying the top pans in place, but do not secure the straps.
Rudder Installation Instructions
To start the rudder installation, partially assemble the AnglerFish by clamping the hull sections together and laying the top pans in place, but do not secure the straps.
Install gudgeon:
Place rudder gudgeon on flat area on the back of stern and flush with top of part. Use an awl to mark the drill point at the center of the bottom oval hole of the gudgeon. Remove gudgeon and use 1/8 inch drill bit to drill hole Add 10-32 x 5/8 inch screw to hold in place. Be sure gudgeon is flush at top of part. Drill second hole using gudgeon as guide and install second screw. Tighten both screws with lock nuts. PRO TIP: with one finger, hold lock nut on surface below holes and slide up into place to start on screw.
Assemble rudder:
Remove cotter pin and metal tube from rudder post and discard, if included. Remove cotter pin from black plastic rudder axle and set both aside.
Install the rudder lift line by sliding equal amounts of line through holes in rudder blade as shown. Be careful to slide lines through side of rudder blade.
Thread line nearest to the third hole back through hole to lock line on rudder. Wind lines on each side of the rudder and install in rudder bracket as shown. Be sure blade is facing correct position and the lines are on opposite sides of the blade and running in opposite directions around hub.
Install rudder hub and cotter pin to connect rudder blade to rudder bracket. Make sure pins on rudder axle are engaged on holes on rudder bracket.
Lead each line through square holes in rudder bracket being sure to keep each line on its correct side.
Install hooks for cable tubes:
Using 1/8 inch drill bit and 8-32 x 1 1/4 inch screws and lock nuts, install one hook 10 inches back from front end of the seat pan and 1 inch in from the side. Hook faces center of kayak. Install second hook on bow side of cup holder ridge 1 inch in from edge and centered on ridge. Hook faces edge of kayak at an angle. Repeat on other side.
Install cable tubes:
Put 3 cable clamps on one of the cable tubes. Leaving 3 inches out the end, install cable clamps with #8 1/2 inch flat head screw. Screw one in at 3 inches from end of raised area on stern top pan so it sits tight in the corner against the pan. PRO TIP: use awl to start drill point. Install the second one about 18 inches from end, lined up just stern of the strap and a third one at about 31 inches from end lined up with the inside of pan. Repeat on the other side.
Install lift line guides:
Starting at the stern, place the first double line guide next to the strap on stern top pan. Center it width wise on the raised area to keep it out of the way of the rudder rest area. Drill 3/16 inch hole. Keep in place with a 10-32 x 1 inch flat head screw. Place the second guide just to the right of the single loop flush with the edge of the raised area. Drill hole, keep in place with screw. Place the third guide just to the right of the next single loop flush with the edge of the raised area. Drill hole, keep in place with screw. Place the fourth guide in line with the cable clamp flush with the edge of the raised area. Drill hole, keep in place with screw.
Secure four double line guides with lock nuts.
Add lift line:
Place rudder in gudgeon and thread the left line through the left side of the double line guides. Thread the right line through the right side of the double line guides.
Connect lift lines to bungee cord by folding end of lift line back about 4 inches and tie overhand knot on each end leaving a loop.
Connect lines by tying bungee cord to each loop with double hitch knot.
Drill a 3/16 inch hole 1 inch in from inside of pan and 1 inch up from floor of pan on side of cup holder on starboard side. Place 10-32 x 5/8 inch screw through pad eye, align pad eye parallel to bottom of pan and drill second hole 1 inch up, using pad eye as guide. Add second screw and tighten both with lock nuts to attach the pad eye.
Add steering lines:
With rudder down and in straight position, thread steering lines through each tube. Tie stern ends loosely to the rudder. At other end, tie overhand knot leaving a loop. Attach s-biner to the loop.
Attach a zip tie to the foot pedal from underside as shown and keeping end to underside of foot pedal. Make loop snug but leave enough room to attach the s-biner. Cut off excess zip tie with pliers. Repeat on other side.
Set line length to foot pedals:
Connect rudder lift line to pad eye with D-biner and put rudder in lifted position. Hook line tubes under hooks.
Adjust foot pedals to proper length for you and lock pedals in place. Attach s-biners to the zip ties that you installed on the foot pedals.Tie steering lines tightly to the rudder being sure to keep the rudder in the center of the rudder rest.
Be sure to test rudder completely before trimming excess line. You may want to leave extra line to allow for adjustment in the future.
Disassembly:
To disassemble, simply unclip s-biners from foot pedals, release tubes from hooks and clip s-biners onto bungee on back pan. Remove r-pin and remove rudder from gudgeon, replace r-pin and tuck under bungees.
That’s it, you are done.